Sign permits in the Phoenix metro: what you need and how long it takes
Almost every outdoor business sign in the Phoenix metro needs a city sign permit before it goes up. Each city has its own rules, forms and fees. Here is how it works, city by city, and what we handle for you.
Do I need a permit for my sign?
For a permanent outdoor business sign such as channel letters, a wall sign, or a monument or pylon sign: almost always yes. Phoenix's zoning code, for example, requires a sign permit before a sign is put up, moved or changed. A few very small signs are exempt in some cities (Scottsdale, for example, does not require a permit for private-property signs of 6 square feet or less). Temporary banners usually need their own temporary sign permit.
A sign put up without a permit can cost more later: Tempe, for example, charges double fees for signs installed before a permit is issued.
Sign permit applications are typically filed by a licensed sign contractor (Tempe, for example, requires it under Arizona rules). Win Signs is licensed by the Arizona Registrar of Contractors (ROC 339111).
The usual order of steps
- Landlord approval first. If you lease, your landlord or property manager approves the sign design. Some cities ask for that approval with the permit (Chandler, for example, asks for a letter or email from the landlord or owner). Landlord sign rules explained →
- Permit drawings. Scaled drawings of the sign (size, materials, how it is lit and mounted) and the building wall or site plan showing where it goes.
- Submit and review. Most cities take sign permits through an online portal. The city may send corrections; we answer them and resubmit.
- Permit approved, then build and install.
- Final inspection. Most cities inspect the sign after it is installed. The permit is not finished until the inspection passes.
Get a free mockup of your sign + a price
Send your business address or a photo of your storefront. We send back your sign on your building with a clear, upfront price within 1 business day.
Get my free mockup →Call (480) 270-4987City by city
| City | What to know |
|---|---|
| Phoenix | Sign permits come from the Planning and Development Department. Wall signs and ground signs are applied for separately. |
| Mesa | Sign permits are reviewed within 10 business days; faster review is available for an extra fee. The sign permit fee is in addition to any building permit. |
| Gilbert | Apply through Gilbert's One Stop Shop portal, with plans showing the sign dimensions and the building elevation with the sign's location. Signs follow the Land Development Code and any approved sign program for the center. |
| Chandler | Submit online. The application needs the contractor details, the job value, landlord or owner authorization and two sets of sign details. Every sign is inspected after install. |
| Tempe | A site plan and elevations are required; the target for the first review is 6 to 10 business days. Signs that do not meet the center's approved sign criteria need a design review first. |
| Scottsdale | Apply through the city's online portal; the application is checked for completeness before review. After the permit is issued, the first inspection must happen within 180 days. |
From each city's official pages as of November 2026. Cities update their forms and fees, so we check the current rules for every job. We also work in Glendale, Peoria, Surprise, Goodyear, Avondale, Queen Creek and the rest of the Valley.
How long does a sign permit take?
Once your landlord approves the sign, the city permit usually takes about 10 days with us, longer if the city asks for corrections. We build and install your sign about 1 week after the permit is approved. If you have an opening date, tell us when you ask for a quote and we plan around it.
What we handle for you
- The landlord approval package: your sign's drawing, size, colors and lighting
- The city permit drawings and the application
- Answering the city's correction requests until the permit is approved
- Paying the city's fee for you, billed at cost with no markup
- The install and the final inspection
You get updates at each step, so you always know where your permit is.
Get a free mockup of your sign + a price
Send your business address or a photo of your storefront. We send back your sign on your building with a clear, upfront price within 1 business day.
Get my free mockup →Call (480) 270-4987